Hi,

 

In Graphical Planning Board (CM33) the slot you are seing the time setup in the work center under Standard Availabe Capacity, Start time and end time.

 

If you want to see the load for the work center based on the Capacity Utilization, No of individual capacity etc you can see in the report CM01.

 

Regards,

R. Loganathan